Azerbaijan, Georgia plan to build new power transmission line by 2025 to increase energy supplies
BAKU. Oct 20 (Interfax) - There are plans to launch a new 500-kilovolt Azerbaijan - Georgia - Turkey border power transmission line by 2025, Azerbaijani Energy Minister Parviz Shahbazov said.
"There are plans to put a new 330-kilovolt two-way Gardabani power transmission line into service by the end of this year in order to increase the capacity of electricity transmission between Azerbaijan and Georgia. Beyond that, there are plans to build a new 500-kilovolt Azerbaijan - Georgia - Turkey border power transmission line by 2025 and expand the converter substation, which will allow for an additional electricity transmission capacity of 700 megawatts," Shahbazov said in an article published in Azerbaijan's Respublika newspaper.
The overall capacity of electricity transmission to Georgia will thus total 1.4 gigawatts and to Turkey 1.05 GW, he said.
Azerbaijani electricity exports totaled 1.67 billion kilowatt-hours in 2021 and 1.8 billion kWh in January-September 2022, up 1.8-fold over the same period of 2021, with 940.5 million kWh going to Turkey, 694.1 million kWh going to Georgia, 95.6 million kWh going to Iran, and 75.6 million kWh going to Russia, Shahbazov said.
Azerbaijan imported 104.9 million kWh of electricity in January-September.
An Azerbaijan - Georgia - Turkey energy bridge was established in 2013 with the launch of the 500-kilovolt Samukh - Gardabani power transmission line, meaning that the technical capabilities were created for the export of electricity from Azerbaijan to Georgia and Turkey and subsequently to countries of the Black Sea region and Eastern Europe.