Investment program of OGK-2 may rise by 16% in 2015, including upgrading by 80%
MOSCOW. May 18 (Interfax) - The financing of the investment program of OJSC OGK-2 in 2015 may rise by 16% to 27.5 billion rubles, the company said in an annual report.
In 2014 the company's investment program was 23.7 billion rubles with VAT.
A large part of the funds will be allocated towards the construction of power generating units according to capacity supply agreements. In particular, 1.4 billion rubles is being allocated the power unit of the Ryazanskaya state district power plant that is under construction, 5.2 billion rubles to the Novocherkasskaya state district power plant, 4.2 billion rubles to the first power unit of the Serovskaya state district power plant, 270 million rubles towards that plant's second unit and 10.6 billion rubles to the Troitskaya state district power plant.
The report noted that this year it is planned to launch new power units at the Troitskaya and Serovskaya state district power plants and also at the Ryazanskaya state district power plant. The company is focusing on Q3 for this.
The program for retrofitting and upgrading in 2015 is forecast at 5.9 billion rubles with VAT against the 3.3 billion rubles that were financed in 2014.
The plan for the financing of servicing new equipment is 1.148 billion rubles, which is four times more than last year.