Act on end of guarantee maintenance of first Bushehr NPP unit to be signed in Sept

MOSCOW. June 3 (Interfax) - The act on the end of guarantee maintenance of the first unit of the Bushehr Nuclear Power Plant in Iran will be signed in September, the president of Rosatom's engineering company NIAEP-ASE, Valery Limarenko told reporters on Tuesday.

"We met with our Iranian colleagues today and received confirmation that the unit is operating splendidly. We expect that the act on the end of guarantee maintenance will be signed in September," Limarenko said.

Negotiations with Iran on the construction of the NPP will develop, he added. "We are now conducting surveys for the second and third units. This year we're starting the main work concerning Bushehr-2," Limarenko said.